Berong nickel project update - drilling to commence
Filed under: Operator - Toledo Mining
Toledo Mining Corporation plc (”Toledo” or the “Company”) (AIM:TMC) is pleased to announce that Berong Nickel Corporation (”BNC”) has received an approved Exploration Permit EP60 to commence its planned drilling programme at the Berong nickel project. A drilling programme of 20,000 metres will commence immediately with six drill rigs which are already on site and is expected to take 12 months to complete. Publication of a revised JORC resource will follow approximately six months after completion. Drilling results will be released as assay results become available during this period.
The goal of this programme is to delineate a JORC resource of over 40 million tonnes of nickel laterite ore, which the Directors consider would be sufficient to support a potential nickel mine producing 20,000 tonnes per annum of nickel.